PERT CPM Calculating ES EF LS and LF indicated on the diagram

PERT CPM Calculating ES EF LS and LF indicated on the diagram

Homework 

 

This homework assignment is based on Swiss (2011), Chapter 1 – Planning Tools: PERT/CPM.

 

Application – CPM

 

For the following problems, show the diagram with ES, EF, LS, and LF indicated on the diagram.

 

1.

Activities Predecessors Duration
A 3
B 5
C A 2
D B 2
E C, D 1
F E 4
G F 5

 

 

2.

Activities Predecessors Duration
A 5
B A 3
C A 2
D A 1
E B, C, D 4
F E 5
G E 6
H E 2

 

 

3.

Activities Predecessors Duration
A 2
B 4
C 3
D A, B, C 3
E A, B, C 1
F D, E 4
G F 4
H G 2
I G 3

 

 

Application 2 – PERT

 

For the following problems, diagram and then show ES, EF, LS, LF, and slack on a separate table.

 

7.

Activities Predecessors Duration
o m p
A 1 14 15
B 4 6 8
C A, B 1 8 15
D A, B 9 9 9
E C 4 9 26
F C 1 2 9
G C 3 4 11
H D 7 9 11
I G, H 2 3 40
J E, F 5 5 5
K I, J 5 6 13