A network consists of the following list. Times are given in weeks. (20 points)
Activity | Preceding | Duration |
A | 6 | |
B | A | 4 |
C | A | 5 |
D | A | 4 |
E | B | 10 |
F | B | 8 |
G | C,F | 3 |
H | D | 3 |
I | H | 8 |
J | G,I | 6 |
K | E,J | 2 |
a. Draw the network diagram.
b. Which activities form the critical path?
c. How much slack exists at each activities?
d. What is the duration of the critical path?